Renovation 2020
At a Special Meeting in May, the Post membership present voted to move forward with the renovation of the Post. A weekly update will be posted each Friday. Questions about the renovation project should be emailed to rebuild@vfw10148.org.

Week ending 09/25/20:
- Dead wiring removed.
- Completed plumbing relocations.
- Project expenditures to date: $22,886.99.

Week ending 09/18/20:
- Electrical completed.
- Ceiling and wall bids compiled.
- Project expenditures to date: $19,712.57.

Week ending 09/11/20:
- Subfloor completed.
- Framing inspection passed.
- Project expenditures to date: $19,508.57.

Week ending 09/04/20:
- Plumbing inspection passed.
- Subfloor 80% installed.
- Project expenditures to date: $19,303.75.