Renovation 2020
Even though our building is being renovated, Post 10148 is still open for the conduct of Post and Auxiliary business including community, youth, and Veteran support activities. The renovation timeline may see additional delays due to the continuing COVID-19 pandemic.

Project updates are posted each Friday. The Post building is open until 4:30 PM on Fridays for any member who would like to stop by to check-out the work in progress. This is your Post. Your involvement matters!

Week ending 10/30/20:
- Worked punch lists for primary contractors.
- Re-engaged secondary contractors lost to October work stoppage.
- No new contract work commenced.
- Project expenditures to date: $39,794.40.

Week ending 10/23/20:
- Bar, dining area, kitchen, and restroom lighting installed.
- Ceiling and interior walls painted by Post volunteers.
- No new contract work commenced.
- Project expenditures to date: $31,794.40.

Week ending 10/16/20:
- Relocation of north entry completed.
- No new contract work commenced.
- Project expenditures to date: $30,413.59.

Week ending 10/09/20:
- Ceiling and interior walls completed.
- Permabase subfloor installed.
- Project expenditures to date: $30,413.59.

Week ending 10/02/20:
- Dining area and bar ceilings resurfaced.
- Bathroom and kitchen ceilings replaced.
- Project expenditures to date: $23,687.02.