At a Special Meeting in May, the Post membership present voted to move forward with the renovation of the Post. A weekly update will be posted each Friday. Questions about the renovation project should be emailed to rebuild@vfw10148.org.

Week ending 06/26/20:
- Completed floor engineering site visit 06/23/20.
- Completed MEP architectural site visit 06/25/20.
- Project expenditures to date: $6,486.03.

Week ending 06/19/20:
- Passed City of Cocoa Beach demo inspection on 06/15/20.
- Awaiting architectural/engineering drawings and signatures.
- Project expenditures to date: $6,054.03.

Week ending 06/12/20:
- Completed demo, inspection scheduled for 06/15/20.
- Disposed over 8 tons of demo debris.
- Project expenditures to date: $5,565.03.

Week ending 06/05/20:
- Facilities Committee approved the primary contractors during a 06/01 meeting.
- Demo nearing completion, disposed of 5.39 tons of demo debris.