At a Special Meeting in May, the Post membership present voted to move forward with the renovation of the Post. A weekly update will be posted each Friday. Questions about the renovation project should be emailed to rebuild@vfw10148.org.

Week ending 07/31/20:
- Architectural and engineering drawings signed and sealed.
- Construction permit application submitted to the City.
- Project expenditures to date: $8,436.03.

Week ending 07/24/20:
- Architectural and engineering drawings approved.
- Updated bids being reviewed against budget.
- Project expenditures to date: $8,436.03.

Week ending 07/17/20:
- Drawings ready for approval pending final Post member review.
- Updated bids being developed as needed based on MEP drawings.
- Project expenditures to date: $8,436.03.

Week ending 07/10/20:
- Sent architectural/engineering plans to sub-contractors for review.
- Reviewed design for through-wall tap system.
- Project expenditures to date: $6,486.03.

Week ending 07/03/20:
- Reviewed final MEP data for architectural drawings.
- Reviewed floor and ramp engineering drawings.