At a Special Meeting in May, the Post membership present voted to move forward with the renovation of the Post. A weekly update will be posted each Friday. Questions about the renovation project should be emailed to rebuild@vfw10148.org.

Week ending 08/28/20:
- Electrical work below floor grade completed.
- Plumbing supply and drain lines installed.
- Project expenditures to date: $13,103.75.

Week ending 08/21/20:
- Sonotube piers poured to level floor beams.
- Electrical and plumbing renovation begun.
- Project expenditures to date: $12,632.15.

Week ending 08/14/20:
- Permit BP-20-2178 issued on 08/12/20.
- Flooring materials delivered on 08/14/20.
- Project expenditures to date: $12,441.32.

Week ending 08/07/20:
- Permit application under review at the City.
- Construction meeting held with contractors on 08/06/20 to sequence work.